1、The project schedule is more than a document that lays out the activities over time to representthe time dimension of the project,it is a management tool to be used for decision making.As such,the schedule is used bythe roject management team to().
A.Measure,delay,record,distribute,analyze,and direct
B.Plan,schedule,monitor,control,report,and forecast
C.Promote,highlight,monitor,control,forecast,and report
D.Emphasize,visualize,analyze,conceptualize,report and record
2、Cloud storage is a model of computer of computer data storage in which the digital data is stored in logical pools.The physical storage spans multiple servers(somentimes in multiple locations),and the physical environment is typically owned and managed by a hosting company.As for the cloud concepet,the cloud storage service is one kind of().
A、IaaS
B、PaaS
C、SaaS
D、DaaS
3、All of followings should be done by the project manager during project control except().
A、Determine that a change has occurred
B、Ensure that a change is agreed
C、Make sure all changes are approved by management
D、Manage changes as they occur
4、在()时。可以不进行招标。
A、需要采用不可替代的专利或者专有技术
B、项目全部或部分使用国有投资或国家融资
C、采购大型关系公共安全的基础设施
D、使用国际组织或外国政府贷款、援助资金
5、GB/T16260-2006对软件质量度量做了详细的规定,其中()可用于开发阶段的非执行软件产品,如标书、需求定义、设计规格说明等。
A.外部度量
B.管理度量
C.使用质量的度量
D.内部度量
(240806)答案
6、C
7、C
8、C
9、D
10、C