慧翔天地管理咨询(北京)有限公司
PMI-PMP®
报考条件 报考费用 报考流程 报考时间 成绩查询 证书领取 备考攻略 每日试题
软考
报考条件 报考费用 报考流程 报考时间 成绩查询 证书领取 备考攻略 每日试题
NPDP®
报考条件 报考费用 报考流程 报考时间 成绩查询 证书领取 备考攻略 每日试题
项目管理专业人员评价(CSPM)
报考条件 报考费用 报考流程 报考时间 成绩查询 证书领取 备考攻略 每日试题
PMI-ACP®
报考条件 报考费用 报考流程 报考时间 成绩查询 证书领取 备考攻略 每日试题
当前位置:慧翔天地 > 新闻热点>PMP备考每日试题(211104)

PMP备考每日试题(211104)

慧翔天地
2021-11-04 14:58:50
  点击量:968
报考资格在线测评
*
*
立即测评

用项目管理挑战年薪三十万

  限时免费领取,2022年度公益大课《巧用项目管理轻松突破职业瓶颈慧翔天地手把手带你轻松学项目管理,从项目管理小白走向职场巅峰5天课程免费学,快乐成长,更有超低PMP®培训优惠,还有豪礼赠送,详情可以直接点击上方图片进入活动报名页。

       每期慧翔天地小编都会附上5~10道PMP®综合测试题,以帮助大家达到练习的效果,本期PMP试题答案会附加在下一期的结尾。大家如果想了解2022年PMP®考试报考流程、报考时间、报考要求PMP®报考费用PMP®考试地点PMP®成绩查询PMP®报考资格测评等等均可访问站内进行了解。

  21、You have always been asked by your management to cut your project estimate by ten percent after you have given it to them.The scope of your new project is unclear and there are over 30 stakeholders.Management expects a 25 percent reduction in downtime as a result of the project.Which of the following is the BEST course of action in this situation?

  A.Re-plan to achieve a 35 percent improvement in downtime.

  B.Reduce the estimates and note the changes in the risk response plan.

  C.Provide an accurate estimate of the actual costs and be able to support it.

  D.Meet with the team to identify where you can find lo percent savings.

  21、你的管理层总是要削减你的项目估算的10%。你的新的项目范围还不清楚,包含30多个项目干系人。管理层预计由于该项目将降低25%的停机时间。这种情况下哪项是最好的解决办法

  A.重新计划获得35%的停机时间改进

  B.减少估算,并在风险应对计划中注明变更

  C.提供准确的实际成本估算并能支撑该结果

  D.会见团队以确认从哪里可以找到10%的节约

  22、ABC company commonly used Sum of the Years method to alculate depreciation on assets.They purchased a computer which cost$15,000,knowing they can sell it at the end of three years for$3,000.How much depreciation is taken the third year?

  A.$4,000

  B.$2,000

  C.$7,500

  D.$2,500ABC

  22、ABC公司通常使用年限总和法来计算资产折旧。他们购买了一台价值$15,000的计算机,并了解到三年后可以卖$3,000。第三年折旧多少

  A.$4,000

  B.$2,000

  C.$7,500

  D.$2,500

  23、During a project manager’s first meeting with the project sponsors.The project management team learns project sponsor expects the product to have a response time of under two seconds.Which aspect of the project quality plan will address this requirement?

  A.Performance acceptance criteria

  B.System outputs

  C.Define scope

  D.Benchmarking

  23.在项目经理和项目发起人的第一次会议上,项目团队意识到项目发起人希望产品的反应速度在2秒钟以下,下列哪一项质量计划可以解决这一需求

  A.性能验收标准

  B.系统输出

  C.定义范围

  D.基准对照

  24、A project management team plans to deploy a new product.Many of the senior leaderships and team members are unfamiliar with the product,the project manager worries that the deployment and testing time of this product will be delay,as the team members lack of relevant knowledge.For reducing project risk and ensure holding a consistent training for the project team members and ensure quality of training,which types of training should be offered?

  A.strategic planning

  B.project resource competency

  C.project risk planning

  D.project budget management

  24.项目管理团队计划推广一项新产品,许多高级领导和业务团队成员都不熟悉该产品,项目经理比较担心,因为团队成员缺乏相关的知识。可能会造成产品的推广和测试时间延迟。若要减少项目风险,保证为项目团队成员举行的培训内容一致并保证培训质量,应该提供下列哪种类型的培训

  A.战略规划培训

  B.项目资源能力培训

  C.项目风险规划培训

  D.项目预算管理培训

  25、Three months into a project,the project manager learns that the project has a CPI of 1.1 and a SPI of 0.84.Three months later the CPI and SPI have changed to 0.9 and 1.0,respectively.In the three month interval,what course of action was likely taken by the project manager?

  A.Reduced project scope

  B.Authorized contingency plan

  C.Increased resources

  D.Reduced resources

  25、项目开展了三个月时,项目经理得知项目的CPI为1.1,SPI为0.84。但三个月后CPI和SPI分别变成0.9和1.0。在这三个月中项目经理有可能采取了什么行动?

  A.减少项目范围

  B.推行应急计划

  C.增加资源

  D.减少资源

      PMP备考每日试题(211103)点击跳转 

      (211103)答案

       16、D

       17、B

       18、C

       19、C

       20、D