PMP备考每日试题(211122)
限时免费领取,2022年度公益大课《巧用项目管理轻松突破职业瓶颈》,慧翔天地手把手带你轻松学项目管理,从项目管理小白走向职场巅峰5天课程免费学,快乐成长,更有超低PMP®培训优惠,还有豪礼赠送,详情可以直接点击上方图片进入活动报名页。
每期慧翔天地小编都会附上5~10道PMP®综合测试题,以帮助大家达到练习的效果,本期PMP试题答案会附加在下一期的结尾。大家如果想了解2022年PMP®考试报考流程、报考时间、报考要求、PMP®报考费用、PMP®考试地点、PMP®成绩查询、PMP®报考资格测评等等均可访问站内进行了解。
76、In which of these organization structures,project managers have rights from medium level to high level?
A.balanced matrix organization
B.strong matrix organization.
C.projectized organization.
D.functional organization.
76、在下列哪一个组织结构中项目经理具有中级到高级的职权
A.平衡矩阵型组织。
B.强矩阵型组织。
C.项目型组织。
D.职能型组织
77、A project manager has a project team consisting of people in four countries.The project is very important to the company,and the project manager is concerned about its success.The length of the project schedule is acceptable.What type of communications method should he use?
A.Informal verbal
B.Formal written
C.Formal verbal
D.Informal written
77、一项目团队由来自4个国家的人组成,该项目很重要,项目经理很担心它能否成功。项目进度规划得很合理。项目经理应该使用何种沟通方法
A.非正式口头
B.正式书面
C.正式口头
D.非正式书面
78、To use statistical quality Control effectively,the project team should know the differences between
A.Prevention and quality control
B.Attribute sampling and variables sampling
C.Attribute sampling and statistical sampling
D.Control limits and operational definitions
78、要有效地使用统计学进行质量控制,项目团队应该分清以下哪两个部分的区别
A.预防与质量控制
B.属性抽样与变量抽样
C.属性抽样与统计抽样
D.控制限制和这个限制的操作定义
79、Of the options below,what is the most significant action the project manager will take for a virtual team project?
A.Send a project plan to all members.
B.Develop a communication management plan.
C.Obtain and analyze team members’expectations.
D.Review the team members’skill.
79、以下各选项中,项目经理会为虚拟团队项目采取的最重要的措施是哪一个
A.将项目计划发放给所有成员。
B.制定一份沟通管理计划。
C.获取并分析团队成员的期望。
D.审查团队成员的技能。
80、Formal written correspondence with the customer is required when:
A.defects are detected.
B.the customer requests additional work not covered under contract.
C.the project has a schedule slippage that includes changes to the critical path.
D.the project has cost overruns.
80、什么情况下要求客户的正式书面答复
A.检测到漏洞
B.客户要求增加合同以外的工作
C.存在项目进度延误,并导致关键路径发生变更
D.项目的成本超支了
(211119)答案
71、A
72、C
73、A
74、B
75、B