PMP备考每日试题(241027)
每期慧翔天地小编都会附上5~10道PMP®综合测试题,以帮助大家达到练习的效果,本期PMP试题答案会附加在下一期的结尾。大家如果想了解2024年PMP®考试报考流程、PMP®报考时间、PMP®报考条件、PMP®报考费用、PMP®报考资格测评等等均可访问站内进行了解。
PMP备考刷题交流群:667625965(点击一键加群)
6、在一个生产线中,控制下限设为301,控制上限设为320.平均值设为310。该过程在下列哪个系列中处于控制中?
A、321.319,315,316.317,310,311,313
B、319,318,309,310,309,310,311,312
C、319,304.307,310.310,301,306,300
D、311,312。319,316,312,311,317,322
7、project requires that a feasibility study be conducted for the s ale of products in a new country.What type of contract should the project manager use
一个项目需要进行在一个新国家销售产品的可行性研究.项目经理应该使用什么合同类型
A、Cost plus award fee(CPAF).成本加奖励费用合同(CPAF)。
B、Cost plus incentive fee(CPIF).成本加激励费用合同(CPIF。
C、Time and material(T&M)工料合同(T&M)。
D、Fixed price with economic price adjustment(FP-EPA)总价加经济价格调整合同(FP-EPA)。
8、A supplier is contracted complete a deliverable in which the buyer will pay the seller's cost as well as provide a 1%fee for each day the deliverable is ahead of deadline.What type of contract would be established with the supplier?()
供应商承包完成某处某项可交付成果,规定买方将会支付卖方的成本且卖方每提前一天完成,买方还支付1%的费用,与供应商签订的合同属于什么类型?()
A、Fixed-price-plus-incentive-fee总价加激励费用合同
B、Cost-plus-incentive-fee成本加激励费用合同
C、Cost-plus-award-fee成本加奖励合同
D、Cost-plus-percentage-of-cost-fee成本加按成本百分比计算奖励合同
9、A company wants to build a device to improve the performance of its best-selling products.The project manager reviews potential vendors that could product the device.What process is the project manager performing?
一家公司希望制造—种装置,改进其销量最高产品的性能。项目经理审查可能生产该装置的潜在供应商。项目经理执行的是哪一个过程?
A、Conduct Procurements实施采购
B、Negotiate Procurementa协商采购
C、Control Procurements控制采购
D、Plan Procurement Management制定采购管理计划
10、一个项目的编码已经完成,然而,团队未能检测到一些缺陷。今后,敏捷团队应该怎么做才能避免这种情况?
A.在sprint开始前确定编码和测试的验收标准
B.确保开发人员听过缩短迭代时间长度来创造更详细的代码
C.使用需求跟踪矩阵,提供返回技术规格的透明性
D.测试团队增加资源,确保开发理想的测试用例
(241026)答案
1、C
2、A
3、A
4、D
5、B