PMP备考每日试题(250305)


每期慧翔天地小编都会附上5~10道PMP®综合测试题,以帮助大家达到练习的效果,本期PMP试题答案会附加在下一期的结尾。大家如果想了解2025年PMP®考试报考流程、PMP®报考时间、PMP®报考条件、PMP®报考费用、PMP®报考资格测评等等均可访问站内进行了解。
PMP备考刷题交流群:667625965(点击一键加群)
6、仆人式领导角色在团队中做出了哪些关键贡献?
A.定义迭代待办事项的内容
B.为团队成员消除障碍
C.向团队成员分配工作
D.创建工作项估算
7、A project is falling behind schedule due to several quality issues that require extensive
rework.The project manager's initial review reveals that design changes were the major cause of this rework.What should the project manager do next?
A.Review the quality management plan to ensure that it has been updated in line with the change log.
B.Ask stakeholders to stop all change requests until the current quality issues are resolved.
C.Instruct the quality manager to present the design changes to the pro1ect team as soon as possible.
D.Defer any new design change requests until the current re work has been resolved.
由于一些需要大量返工的质量问题,一个项目落后于进度。项目经理的初步审查表明,设计变更是这次返工的主要原因。项目经理下一步应该做什么?
A、审核质量管理计划以确保已更新该计划,与变更日志保持一致。
B、要求相关方在当前质量问题得到解决之前停止所有变更请求。
C、指示质量经理尽快向项目团队展示设计变更。
D、推迟任何新的设计变更请求,直到解决当前的返工问题为止。
8、项目经理识别了一项对项目可交付成果具有最高潜在影响的风险,可能导致项目产生重大损失。项目经理执行的是下列哪项?()
A、预期货币价值分析
B、敏感性分析
C、专家判断
D、蒙特卡洛分析
9、项目经理在项目过程中持续地收集项目需求,并不断地对项目范围进行更新和定义。每个月,项目经理从范围文件上选择部分需求实施。项目经理使用了哪份文件?
A、项目范围说明书
B、产品未完项
C、需求文件
D、需求跟踪矩阵
10、已经决定使用瀑布管理项目。然而,由于需求不明确,软件将在短时间内使用Scrum进行开发。在从组织内部获得团队之后,项目经理意识到组织在几个关键领域缺乏技术专长,将需要从供应商获得外部资源。然而,本组织希望保留其对所进行工作的战略酌处权。对于项目经理来说,为了最大限度地与供应商协作,最好的承包技术是什么?
A:团队扩充
B:提前取消选项
C:固定价格增量
D:时间和材料限制
It has been decided that the project will be managed using waterfall.However,due to ambiguous requirements,the software will be developed in short iterations using Scrum.After acquiring a team from within the organization,the project manager realizes that the organization lacks technical expertise in several key areas and will require external resources from a vendor.The organization,however,wants to preserve its strategic discretion on the work performed.What is the best contracting technique for the project manager to use to maximize collaboration with the vendor?
A.Team augmentation
B.Early cancellation option
C.Fixed-price increments
D.Not-to-exceed time and materials
(250304)答案
1、B
2、D
3、C
4、A
5、B