16、Receiving formal confirmation that a project has met or exceeded customer requirements is an essential part of project management.Such confirmation includes,all the following except
A.Formal customer acceptance of project results
B.Meeting requirements of the delivering organization,such as staff evaluations,budget reports,and lessons learned
C.Formal customer acceptance of deliverables
D.Passing a quality control inspection
16、项目符合或者超过了客户要求的正式确认对于项目管理是必要的。这样的确认不包括下列哪一个方面
A.客户对项目结果的正式接收
B.符合承担项目组织的要求:包括人员考核、预算报告和经验总结
C.客户对项目交付成果的正式接收
D.通过了质量控制检查
17、The asphalt highway project that the project manager is managing is 50%complete.The PM planned on having 4,000 square yards of asphalt placed by now,but in actuality.They’ve finished placing 8,000 square yards.The estimated cost forth is work was$1 per square yard.The actual cost for this work is$8,000.What does this tell the project manager?
A.EV is 2.
B.SPI is 2.
C.SPI is 0.50.
D.SV is 0.50
17、项目经理管理的沥青公路项目已完工50%。项目经理原本计划到现在为止铺4000平方码的沥青。而实际上他们已经铺完了8000平方码。这项工作的估算成本为1美元/平方码,实际花费8000美元。这告诉项目经理什么信息?
A.EV is 2.
B.SPI is 2.
C.SPI is 0.50.
D.SV is 0.50
18、The development of a new software application had been completed on time and within budget although resources were new to the technology.During the code install,it was determined that certain aspects of the hardware needed to be configured before the new application could be utilized.The customer was incredibly upset and disappointed as this would cause a delay in the implementation.What could have been the cause for this situation?
A.The customer did not request the hardware to be appropriately set up.
B.The hardware configuration was too expensive and would have caused the project to run over budget.
C.A work breakdown structure was not created adequately.
D.The resources completed a three-week training course versus a more through sixweek training course.
18、虽然项目人员对技术都比较陌生,但还是在规定的时间和预算内完成了一个新软件应用程序的开发。在安装代码过程中,他们确定在新的应用程序可被使用之前,需要对硬件的某些方面进行配置。客户显得非常沮丧和失望,因为如果要进行配置,将会造成项目的实施延误。下列哪一项有可能是发生这种情况的原因?
A.客户未要求对硬件进行适当设置
B.硬件配置太昂贵将会导致项目超支
C.未充分创建工作分解结构
D.项目人员完成了三周的培训课程而不是更为全面的六周培训课程
19、Payment bonds are often required by the contract and require specific actions under the stated conditions.Payment bonds are specifically designed to ensure that the prime contractor provides payment of-
A.Insurance premiums
B.Weekly payrolls
C.Subcontractors,laborers,and sellers of material
D.Damages for accidents caused
19、合同经常规定付款保证金,并要求在一定的条件下采取特定的行动。付款保证金是特别设计用来保证总承包商支付
A.保险费
B.周薪
C.分包商、工人和原料供应商
D.赔偿事故损失
20、While testing the strength of concrete poured on your project,you discover that over 35 percent of the concrete does not meet your company's quality standards.You feel certain the concrete will function as it is,and you don't think the concrete needs to meet the quality level specified.What should you do?
A.Change the quality standards to meet the level achieved.
B.List in your reports that the concrete simply"meets our quality needs."
C.Ensure the remaining concrete meets the standard.
D.Report the lesser quality level and try to find a solution.
20、在测试项目浇注的混凝土强度时,你发现超过35%的混凝土没有符合你的公司的质量标准。你肯定混凝土也会正常工作,你认为混凝土不需要符合该质量标准。你应该怎么办
A.改变质量标准以符合已达到的标准
B.在你的报告里说明混凝土完全“符合我们的需要”
C.确保剩余的混凝土符合标准
D.报告次要的质量水平,并试图找到解决办法
(211102)答案
11、D
12、A
13、D
14、A
15、D