PMP备考每日试题(211213)
限时免费领取,2022年度公益大课《巧用项目管理轻松突破职业瓶颈》,慧翔天地手把手带你轻松学项目管理,从项目管理小白走向职场巅峰5天课程免费学,快乐成长,更有超低PMP®培训优惠,还有豪礼赠送,详情可以直接点击上方图片进入活动报名页。
每期慧翔天地小编都会附上5~10道PMP®综合测试题,以帮助大家达到练习的效果,本期PMP试题答案会附加在下一期的结尾。大家如果想了解2022年PMP®考试报考流程、报考时间、报考要求、PMP®报考费用、PMP®考试地点、PMP®成绩查询、PMP®报考资格测评等等均可访问站内进行了解。
PMP刷题学习交流QQ群:667625965(点击一键加群)
151、A number of tools and techniques are helpful in integrated change control,if you want to assess whether variances form the plan require corrective action,you should use
A.Configuration management software
B.A project management information system
C.Project status review meetings
D.Performance measurement techniques
151、大量的工具和技术对于整合变更控制的过程是非常有帮助的。如果你想评估偏离了原计划的项目是否需要矫正行为,你应该使用
A.范围变更管理软件
B.一个项目管理信息系统
C.项目状态评估会议
D.绩效测评技术
152、An output of close project or phase is the creation of:
A.project archives.
B.a project charter.
C.a project management plan.
D.a risk analysis plan.
152、结束项目或阶段的输出是创建了
A.项目档案
B.项目章程
C.项目管理计划
D.风险分析计划
153、Which of the following is included in a project charter?
A.Identification of risks
B.Work package estimates
C.Detailed resource estimates
D.The business need for the project
153、以下哪项包含在项目章程里
A.风险识别
B.工作包评估
C.详细的资源评估
D.项目的业务需求
154、A company is implementing a project to migrate staff from several buildings to one centralized building.The company contract transfers 100 of the financial risks of this migration to a contractor.What type of contract does the company have
A.Cost-plus-incentive fee
B.Fixed-price
C.Cost-plus-fixed-fee
D.Time and material
154、一家公司正在实施一个项目,将人员从多个办公地点搬移到一个集中的办公地点。公司通过合同已将此次搬迁100%的财务风险都转移给承包商。该公司签订的合同属于什么类型?
A.成本加奖励酬金合同
B.固定总价合同
C.成本加固定酬金合同
D.工料合同
155、Most projects require change because they typically represent something unique of different for the organization.You want to minimize the impact of project changes and you want to ensure that change is managed when and if it occurs.One way to do this is to maintain the original defined project scope and the integrated performance baseline.This can be done through each of the following ways except
A.Rejecting new changes
B.Approving changes and incorporating them into a revised baseline
C.Continuously managing baseline changes
D.Ensuring that project scope changes are reflected in changes to product scope
155、大多数项目实施过程中会出现一些变更,使得项目最终的结果可能偏离最初预期的结果。因此,作为项目经理,你需要尽量地减小变更的影响,并确保在这些变更发生的时候得到适当的管理。一种可以帮助你达到这个目的的方法是保持项目最初定义的范围和整体的业绩基线。以下这些做法中哪一项不能帮助你达到这个目的
A.拒绝新的变更
B.接受出现的各种变更,并将其与原有的基准线相结合,制作出新的基准线
C.持续不断地管理基准线上出现的变化
D.确保项目范围变更在产品范围变更中得到反映
(211210)答案
146、B
147、A
148、D
149、B
150、B